392 inventoried bridges · 1 closed · 17 posted · 4 rated poor · 2025 National Bridge Inventory
United States Bridge Conditions2025 National Bridge Inventory, FHWACompiled
GoodFairPoor All 392 bridges.
4 of the 392 bridges the federal inventory lists in DeKalb County are rated poor; the rest split 291 good and 97 fair.
- 4 of the 392 bridges in DeKalb County, Georgia, are rated in poor condition (1.0%) in the 2025 National Bridge Inventory, as of .
- DeKalb County has 1 bridge closed to all traffic and 17 bridges posted with load restrictions in the 2025 National Bridge Inventory (NBI item 41).
- Since the 2024 inventory, no bridges dropped into poor condition and 2 bridges improved out of it; 23 bridges had at least one major component rating lowered, 2 newly load-posted.
- 1 bridge has a deck, superstructure, substructure or culvert rated 2 (critical) or lower, the bottom of FHWA's 0-9 scale.
- Inspection dates on record run from February 2023 to August 2024; 1 bridge over water is coded scour critical.
- 291 bridges (74.2%) are rated good and 97 (24.7%) fair.
- The median DeKalb County bridge was built in 1967.
- The busiest poor-rated bridge is Houston Mill Road over S Fork Peachtree Creek (built 1958), carrying about 12,400 vehicles a day.
What this page is: the federal bridge inspection inventory for DeKalb County: inspector ratings, closures and load postings as reported by the Georgia DOT for the 2025 inventory. It is not a log of incidents, failures or news events.
Good 74.2% · Fair 24.7% · Poor 1.0% of 392 bridges
What changed since the 2024 inventory
Each bridge's 2025 record compared with its 2024 record under the same structure number: condition class, the 0-9 component ratings, and whether it is open, posted or closed. These are changes in inspection ratings, not reports of incidents.
Bridges whose rating or status got worse
Bridges that improved
| Bridge | What changed | 2024 | 2025 | Vehicles/day |
|---|---|---|---|---|
| US 78 Wbl over M-9218 Valley Brook Rd | fair to good; deck up 6 to 7; superstructure up 7 to 8; substructure up 6 to 7 | Fair | Good | 88,200 |
| US 78 Ebl over M-9218 Valley Brook Rd | fair to good; deck up 6 to 8; substructure up 6 to 7 | Fair | Good | 75,200 |
| Snapfinger Road over Snapfinger Creek | poor to good; superstructure up 4 to 7 | Poor | Good | 30,000 |
| Lawrenceville Hwy. over SR 410 | fair to good; deck up 6 to 7 | Fair | Good | 22,700 |
| Park Drive over Snapfinger Creek | reopened; poor to good; deck up 1 to 8; superstructure up 6 to 8 | Poor | Good | 2,047 |
1 structure in the 2025 inventory does not appear in 2024 under the same number (new or renumbered), and 1 structure listed in 2024 is no longer listed under its number (replaced, removed or renumbered).
Closed and load-posted bridges
Bridges coded closed, posted for load, or open only with temporary measures in NBI item 41. A load posting limits the weight a bridge may carry; it is how owners keep a weakened bridge in service safely.
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Cedar Grove Road over NS Railroad | closed | 1965 | 11,000 | March 2024 | Poor |
| N. Druid Hills Rd. over NS Railroad | posted for load | 1963 | 29,700 | July 2024 | Fair |
| Hairston Road over CSX Railroad | posted for load | 1963 | 22,400 | June 2024 | Fair |
| Pantherville Road over South River | posted for load | 1962 | 16,100 | March 2024 | Fair |
| Johnson Ferry over Nancy Creek | posted for load | 1979 | 14,300 | July 2024 | Fair |
| Houston Mill Road over S Fork Peachtree Creek | posted for load | 1958 | 12,400 | July 2024 | Poor |
| Mercer Univ. Drive over N Fork Peachtree Creek | posted for load | 1967 | 8,060 | July 2024 | Fair |
| Mill Creek Road over Nancy Creek | posted for load | 1965 | 3,290 | July 2024 | Fair |
| N. Dekalb Mall Acc over S Fork Peachtree Creek | posted for load | 1967 | 2,950 | May 2024 | Good |
| Covered Br. Lane over Stone Mountain Creek | posted for load | 1891 | 2,202 | August 2024 | Fair |
| Casa Drive over S Fork Peachtree Creek | posted for load | 1957 | 2,047 | May 2024 | Fair |
| Hearn Road over Corn Creek | posted for load | 1956 | 2,047 | March 2024 | Fair |
| Lullwater Pkwy over Lullwater Creek | posted for load | 1956 | 2,047 | April 2024 | Good |
| Lullwater Pkwy over Lullwater Creek | posted for load | 1956 | 2,047 | April 2024 | Good |
| Presidential Drive over N Fork Peachtree Creek | posted for load | 1967 | 2,047 | July 2024 | Poor |
| Rt. Frontage Road over S Fork Peachtree Creek | posted for load | 1967 | 2,047 | May 2024 | Fair |
| W/B Century Blvd over N Fork Peachtree Creek | posted for load | 1971 | 2,004 | June 2024 | Fair |
| Key Road over Entrenchment Creek | posted for load | 1958 | 1,600 | March 2024 | Good |
Status is as reported for the federal inventory, not live. Closures and postings made since then are published by the Georgia department of transportation and the county road department.
Inspections, scour and other flags
Routine inspection intervals (NBI item 91): 392 on 24 months. Federal rules set 24 months as the regular maximum, require 12 months or less for bridges with a component rated 3 or lower, and allow up to 48 months for bridges in good shape (23 CFR 650.311).
The most recent inspection on record in DeKalb County is dated August 2024; 390 bridges have an inspection dated in 2024.
Scour critical (item 113): 1 bridge; 81 with unknown foundations. Scour critical means the foundations were found unstable for the assessed or calculated scour, the streambed erosion that floods cause around piers and abutments. Fracture critical (item 92A): 1 bridge. These have steel tension members without a redundant load path and get their own scheduled inspections.
Scour-critical bridges
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| US-17 (SR-5) over St. Marys River | open | 1927 | 4,600 | April 2024 | Fair |
Bridges with a component rated 2 or lower
2 is critical, 1 imminent failure, 0 failed and out of service on FHWA's scale. Most such bridges are closed or posted.
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Cedar Grove Road over NS Railroad | closed | 1965 | 11,000 | March 2024 | Poor |
Bridges rated poor
Every bridge in the county with a poor rating, busiest first. Poor means a major component is rated 4 or lower on FHWA's 0-9 scale; it is a repair flag, not a closure notice.
| Bridge | Built | Vehicles/day | Condition |
|---|---|---|---|
| Houston Mill Road over S Fork Peachtree Creek | 1958 | 12,400 | Poor |
| Cedar Grove Road over NS Railroad | 1965 | 11,000 | Poor |
| Presidential Drive over N Fork Peachtree Creek | 1967 | 2,047 | Poor |
| Stokes Road over St. Marys River | 1978 | 110 | Poor |
Busiest bridges in the county
| Bridge | Built | Vehicles/day | Condition |
|---|---|---|---|
| I-85 over N Fork Peachtree Creek | 1957 | 296,000 | Good |
| I-285 over SR 13 Buford Highway | 1958 | 234,000 | Good |
| I-285 over N Fork Nancy Creek | 1960 | 230,000 | Good |
| I-285 over Nancy Creek | 1961 | 225,000 | Good |
| I-285 over SR 141 Ptree Ind. Blvd. | 1961 | 225,000 | Fair |
| I-285 Ramp over SR 141 Ptree Ind. Blvd. | 2023 | 225,000 | Good |
| I-285 over I-85- I-85 Ramp | 1968 | 219,000 | Fair |
| I-85 over M-9217 Access Rd Turn | 1981 | 216,000 | Good |
| I-85 over SR 155- 2 U-turns 3x-ref | 1981 | 216,000 | Good |
| I-285 Ccbl over SR 410 Rmp to I-285 Cbl | 1968 | 213,000 | Fair |
Frequently asked questions
Are any bridges closed in DeKalb County, Georgia?
1 bridge of the 392 in DeKalb County is coded closed to all traffic in the 2025 National Bridge Inventory, and 17 bridges are posted with load restrictions. The inventory is compiled annually; for closures since then, check the Georgia department of transportation.
Have any bridges failed in DeKalb County?
The National Bridge Inventory records inspection ratings, not incidents, so it cannot say whether a bridge failed or made the news. What it does record for DeKalb County: 1 bridge with a component rated 2 (critical) or lower, 4 bridges rated poor overall, and no bridges that dropped into poor condition since the 2024 inventory.
When were bridges in DeKalb County last inspected?
Inspection dates in the 2025 inventory for DeKalb County run from February 2023 to August 2024. Intervals: 392 on 24 months. Most bridges must be inspected at least every 24 months.
Source: FHWA National Bridge Inventory, 2025 (compared with 2024). Counts cover inventoried highway bridges over 20 feet; ratings are reported by the state DOT.
Every bridge in DeKalb County → - all 392, busiest first, each with its own condition record.
All of Georgia: Georgia bridge conditions by county · closed and posted bridges nationwide · every download on the data page.
Background: how bridge ratings work · what "poor" and "structurally deficient" actually mean · how often bridges are inspected.