Bridge conditions in Angelina County, Texas
185 inventoried bridges · 0 closed · 11 posted · 0 rated poor · 2025 National Bridge Inventory
United States Bridge Conditions2025 National Bridge Inventory, FHWACompiled
GoodFair All 185 bridges.
None of the 185 inventoried bridges in Angelina County are rated in poor condition in the current federal inventory. 84 are rated good and 101 fair.
- 0 of the 185 bridges in Angelina County, Texas, are rated in poor condition (0.0%) in the 2025 National Bridge Inventory, as of .
- Angelina County has no bridges closed to all traffic and 11 bridges posted with load restrictions in the 2025 National Bridge Inventory (NBI item 41).
- Since the 2024 inventory, no bridges dropped into poor condition and no bridges improved out of it; 17 bridges had at least one major component rating lowered, 1 newly load-posted.
- Inspection dates on record run from May 2022 to September 2024; 4 bridges over water are coded scour critical.
- 84 bridges (45.4%) are rated good and 101 (54.6%) fair.
- The median Angelina County bridge was built in 1980.
What this page is: the federal bridge inspection inventory for Angelina County: inspector ratings, closures and load postings as reported by the Texas DOT for the 2025 inventory. It is not a log of incidents, failures or news events.
Good 45.4% · Fair 54.6% · Poor 0.0% of 185 bridges
What changed since the 2024 inventory
Each bridge's 2025 record compared with its 2024 record under the same structure number: condition class, the 0-9 component ratings, and whether it is open, posted or closed. These are changes in inspection ratings, not reports of incidents.
Bridges whose rating or status got worse
| Bridge | What changed | 2024 | 2025 | Vehicles/day |
|---|---|---|---|---|
| Ben Dunn Rd over Crawford Creek | newly posted for load | Fair | Fair | 33 |
| FM 819 over Hurricane Creek | good to fair; superstructure 7 to 6; substructure 7 to 6 | Good | Fair | 8,748 |
| Fdr 303 over Big Creek | good to fair; superstructure 7 to 6; substructure 7 to 6 | Good | Fair | 140 |
| Fdr 303 over South Prong Creek | good to fair; deck 7 to 6; substructure 7 to 6 | Good | Fair | 140 |
| Fdr 314 over Graham Creek | good to fair; substructure 7 to 6 | Good | Fair | 80 |
| US 69 over Biloxi Creek | substructure 6 to 5 | Fair | Fair | 18,129 |
| US 59 NB over Neches River | substructure 7 to 6 | Fair | Fair | 10,751 |
| US 59 SB over White Oak Creek | deck 7 to 6 | Fair | Fair | 8,364 |
| US 69 over Dry Creek | culvert 9 to 7 | Good | Good | 5,922 |
| US 69 SB over Shawnee Creek | deck 8 to 7; superstructure 9 to 8 | Good | Good | 6,279 |
| US 69 over SH 63 and Sandy Creek | deck 8 to 7; superstructure 9 to 8 | Good | Good | 3,234 |
| US 69 NB over Shawnee Creek | deck 8 to 7; superstructure 9 to 8 | Good | Good | 3,200 |
| US 59 SB U-turn over US 59 | substructure 8 to 7 | Good | Good | 500 |
| US 69 NB Exit over Sandy Creek | superstructure 9 to 8; substructure 8 to 7 | Good | Good | 500 |
| US 69 NB over Wetlands 2 | superstructure 9 to 8 | Good | Good | 6,279 |
| US 69 SB over Wetlands | superstructure 9 to 8 | Good | Good | 6,279 |
| US 69 On-Ramp over Sandy Creek | deck 9 to 8; superstructure 9 to 8 | Good | Good | 3,100 |
| US 69 NB On-Ramp over Wetlands | superstructure 9 to 8 | Good | Good | 1,500 |
Bridges that improved
| Bridge | What changed | 2024 | 2025 | Vehicles/day |
|---|---|---|---|---|
| SH 94 over Cedar Creek | fair to good; culvert up 6 to 7 | Fair | Good | 13,640 |
| SH 147 over Rocky Creek | fair to good; culvert up 6 to 7 | Fair | Good | 2,085 |
| FM 1818 over Stovall Creek | fair to good; culvert up 6 to 7 | Fair | Good | 984 |
2 structures in the 2025 inventory do not appear in 2024 under the same number (new or renumbered), and no structures listed in 2024 are no longer listed under their number (replaced, removed or renumbered).
Closed and load-posted bridges
Bridges coded closed, posted for load, or open only with temporary measures in NBI item 41. A load posting limits the weight a bridge may carry; it is how owners keep a weakened bridge in service safely.
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Hall St over White Oak Creek | posted for load | 1998 | 1,005 | June 2023 | Fair |
| Daniel Mccall Dr over Bradley Branch | posted for load | 1927 | 598 | June 2023 | Fair |
| Old Hwy 69 over Buck Creek | posted for load | 1927 | 164 | June 2023 | Fair |
| Old Hwy 69 over Buck Creek Relief | posted for load | 1927 | 164 | June 2023 | Fair |
| Marshall Ivy Rd over Shawnee Creek Relief | posted for load | 1922 | 92 | June 2023 | Fair |
| Marshall Ivy Rd over Shawnee Creek Relief | posted for load | 1922 | 92 | June 2023 | Fair |
| Tidwell Rd over Trib of Bradley Branch | posted for load | 1992 | 80 | June 2023 | Fair |
| Wilkerson Rd over Willis Creek | posted for load | 1998 | 66 | June 2023 | Fair |
| Id Anderson Rd over Anderson Creek | posted for load | 1998 | 50 | June 2023 | Fair |
| Ben Dunn Rd over Crawford Creek | posted for load | 2002 | 33 | June 2023 | Fair |
| Kirtley Rd over Red Bayou | posted for load | 1948 | 10 | June 2023 | Fair |
Status is as reported for the federal inventory, not live. Closures and postings made since then are published by the Texas department of transportation and the county road department.
Inspections, scour and other flags
Routine inspection intervals (NBI item 91): 4 on 12 months or less, 165 on 24 months, 16 on 48 months. Federal rules set 24 months as the regular maximum, require 12 months or less for bridges with a component rated 3 or lower, and allow up to 48 months for bridges in good shape (23 CFR 650.311).
The most recent inspection on record in Angelina County is dated September 2024; 113 bridges have an inspection dated in 2024.
Scour critical (item 113): 4 bridges; 14 over water not yet evaluated for scour. Scour critical means the foundations were found unstable for the assessed or calculated scour, the streambed erosion that floods cause around piers and abutments. Fracture critical (item 92A): 4 bridges. These have steel tension members without a redundant load path and get their own scheduled inspections.
Scour-critical bridges
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| US 59 NB over White Oak Creek | open | 1947 | 10,351 | May 2024 | Fair |
| FM 841 over Biloxi Creek | open | 2019 | 1,700 | May 2024 | Good |
| FM 2497 over Jack Creek Relief | open | 1963 | 944 | May 2024 | Fair |
| DANIEL McCALL DR over Moccasin Creek | open | 2013 | 840 | September 2024 | Good |
Bridges rated poor
No bridges in this county carry a poor rating in the current inventory.
Busiest bridges in the county
| Bridge | Built | Vehicles/day | Condition |
|---|---|---|---|
| Lp 287 over FM 325 | 1974 | 39,510 | Fair |
| Lp 287 & US 59 over FM 841 | 1988 | 38,262 | Good |
| Lp 287 over Cedar Creek | 1961 | 33,190 | Fair |
| US 59NB Dir Conn over Bus 59 & Lp 287 | 2014 | 32,598 | Good |
| Lp 287 & US 59 over Bus 69 | 1971 | 32,000 | Fair |
| Lp 287 over FM 324 & Sprr | 1961 | 30,952 | Fair |
| Lp 287 & US 59 over UPRR | 1971 | 30,000 | Fair |
| Lp 287 & US 59 over Shirey Creek | 1971 | 30,000 | Fair |
| Sl 287 over Hurricane Creek | 1962 | 28,577 | Fair |
| US 59 over Mill Creek | 1943 | 28,456 | Fair |
Frequently asked questions
Are any bridges closed in Angelina County, Texas?
No bridges of the 185 in Angelina County are coded closed to all traffic in the 2025 National Bridge Inventory, and 11 bridges are posted with load restrictions. The inventory is compiled annually; for closures since then, check the Texas department of transportation.
Have any bridges failed in Angelina County?
The National Bridge Inventory records inspection ratings, not incidents, so it cannot say whether a bridge failed or made the news. What it does record for Angelina County: no bridges with a component rated 2 (critical) or lower, no bridges rated poor overall, and no bridges that dropped into poor condition since the 2024 inventory.
When were bridges in Angelina County last inspected?
Inspection dates in the 2025 inventory for Angelina County run from May 2022 to September 2024. Intervals: 4 on 12 months or less, 165 on 24 months, 16 on 48 months. Most bridges must be inspected at least every 24 months.
Source: FHWA National Bridge Inventory, 2025 (compared with 2024). Counts cover inventoried highway bridges over 20 feet; ratings are reported by the state DOT.
Every bridge in Angelina County → - all 185, busiest first, each with its own condition record.
All of Texas: Texas bridge conditions by county · closed and posted bridges nationwide · every download on the data page.
Background: how bridge ratings work · what "poor" and "structurally deficient" actually mean · how often bridges are inspected.