Bridge conditions in Petersburg Borough, Alaska

137 inventoried bridges · 2 closed · 2 posted · 11 rated poor · 2025 National Bridge Inventory

United States Bridge Conditions2025 National Bridge Inventory, FHWACompiled

GoodFairPoor All 137 bridges.

11 of the 137 bridges the federal inventory lists in Petersburg Borough are rated poor; the rest split 63 good and 63 fair.

What this page is: the federal bridge inspection inventory for Petersburg Borough: inspector ratings, closures and load postings as reported by the Alaska DOT for the 2025 inventory. It is not a log of incidents, failures or news events.

Good 46.0% · Fair 46.0% · Poor 8.0% of 137 bridges

What changed since the 2024 inventory

Each bridge's 2025 record compared with its 2024 record under the same structure number: condition class, the 0-9 component ratings, and whether it is open, posted or closed. These are changes in inspection ratings, not reports of incidents.

0
dropped into poor
since 2024
0
improved out of poor
since 2024
8
had a rating lowered
deck, superstructure, substructure or culvert
1
newly closed or posted
1 closed, 0 posted

Bridges whose rating or status got worse

BridgeWhat changed20242025Vehicles/day
43500 over Lognewly closedPoorPoor5
Logging Road over Streamgood to fair; substructure 7 to 6GoodFair50
No Data Entered over No Data Enteredgood to fair; substructure 7 to 6GoodFair50
Logging Road over Streamgood to fair; superstructure 7 to 6GoodFair30
No Data Entered over No Data Enteredgood to fair; superstructure 7 to 6GoodFair–
Logging Road over Streamsubstructure 6 to 5; superstructure up 5 to 6FairFair–
No Data Entered over No Data Entereddeck 6 to 5; superstructure 6 to 5PoorPoor–
Logging Road over Streamdeck 7 to 6; substructure 7 to 6FairFair5
Logging Road over Streamsuperstructure 8 to 7GoodGood50

Bridges that improved

BridgeWhat changed20242025Vehicles/day
Logging Road over Streamfair to good; deck up 5 to 7FairGood5
Logging Road over Streamfair to good; superstructure up 6 to 7FairGood5
Logging Road over Streamfair to good; superstructure up 6 to 7FairGood5
Logging Road over Streamfair to good; superstructure up 6 to 7FairGood–
Logging Road over Streamfair to good; deck up 6 to 7FairGood–
Logging Road over Creekfair to good; superstructure up 6 to 7FairGood–

no structures in the 2025 inventory do not appear in 2024 under the same number (new or renumbered), and 4 structures listed in 2024 are no longer listed under their number (replaced, removed or renumbered).

Closed and load-posted bridges

Bridges coded closed, posted for load, or open only with temporary measures in NBI item 41. A load posting limits the weight a bridge may carry; it is how owners keep a weakened bridge in service safely.

BridgeStatus (item 41)BuiltVehicles/dayLast inspectedCondition
Ifa Ferry Route over Petersburg S Mitkof Termclosed20062,659May 2023Good
43500 over Logclosed20025August 2023Poor
Birch Street over Birch Street Viaductposted for load1960200May 2023Fair
Sing Lee Alley over Rasmus Enge Bridgeposted for load1945100May 2023Fair

Status is as reported for the federal inventory, not live. Closures and postings made since then are published by the Alaska department of transportation and the county road department.

Inspections, scour and other flags

Routine inspection intervals (NBI item 91): 2 on 12 months or less, 108 on 24 months, 27 on 48 months. Federal rules set 24 months as the regular maximum, require 12 months or less for bridges with a component rated 3 or lower, and allow up to 48 months for bridges in good shape (23 CFR 650.311).

The most recent inspection on record in Petersburg Borough is dated September 2024; 48 bridges have an inspection dated in 2024.

Scour critical (item 113): 3 bridges. Scour critical means the foundations were found unstable for the assessed or calculated scour, the streambed erosion that floods cause around piers and abutments. Fracture critical (item 92A): 21 bridges. These have steel tension members without a redundant load path and get their own scheduled inspections.

Scour-critical bridges

BridgeStatus (item 41)BuiltVehicles/dayLast inspectedCondition
Kake Access - Usfs over Creek Name Not Listedopen198110May 2023Fair
Kake Access - Usfs over Creek Name Not Listedopen198010May 2023Fair
Kake Access - Usfs over Creek Name Not Listedopen198110May 2023Fair

Bridges with a component rated 2 or lower

2 is critical, 1 imminent failure, 0 failed and out of service on FHWA's scale. Most such bridges are closed or posted.

BridgeStatus (item 41)BuiltVehicles/dayLast inspectedCondition
Logging Road over Streamopen200310August 2023Poor

Bridges rated poor

Every bridge in the county with a poor rating, busiest first. Poor means a major component is rated 4 or lower on FHWA's 0-9 scale; it is a repair flag, not a closure notice.

BridgeBuiltVehicles/dayCondition
Kake Access - Usfs over Muskeg Creek198110Poor
Logging Road over Stream200310Poor
43500 over Log20025Poor
43500 over Log20025Poor
43506 over Log20025Poor
43506 over Log20025Poor
43506 over Log20025Poor
No Data Entered over No Data Entered20045Poor
Logging Road over Stream1981–Poor
Logging Road over Stream1981–Poor
No Data Entered over No Data Entered2006–Poor

Busiest bridges in the county

BridgeBuiltVehicles/dayCondition
Nordic Drive over Hammer Slough19744,210Fair
Ifa Ferry Route over Petersburg S Mitkof Term20062,659Good
Irr:ptrsbg/kake Rd over Gunnuk Creek1981770Fair
Mitkof Highway over Twin Creek1996760Good
Irr:keku Rd (kake) over Sitkum Creek2011270Fair
Birch Street over Birch Street Viaduct1960200Fair
Mitkof Highway over Falls Creek1967180Fair
Sing Lee Alley over Rasmus Enge Bridge1945100Fair
Mitkof Highway over Unnamed Creek Mp 25.42011100Good
Mitkof Highway over Ohmer Creek200780Good

Frequently asked questions

Are any bridges closed in Petersburg Borough, Alaska?

2 bridges of the 137 in Petersburg Borough are coded closed to all traffic in the 2025 National Bridge Inventory, and 2 bridges are posted with load restrictions. The inventory is compiled annually; for closures since then, check the Alaska department of transportation.

Have any bridges failed in Petersburg Borough?

The National Bridge Inventory records inspection ratings, not incidents, so it cannot say whether a bridge failed or made the news. What it does record for Petersburg Borough: 1 bridge with a component rated 2 (critical) or lower, 11 bridges rated poor overall, and no bridges that dropped into poor condition since the 2024 inventory.

When were bridges in Petersburg Borough last inspected?

Inspection dates in the 2025 inventory for Petersburg Borough run from August 2021 to September 2024. Intervals: 2 on 12 months or less, 108 on 24 months, 27 on 48 months. Most bridges must be inspected at least every 24 months.

Source: FHWA National Bridge Inventory, 2025 (compared with 2024). Counts cover inventoried highway bridges over 20 feet; ratings are reported by the state DOT.

Every bridge in Petersburg Borough → - all 137, busiest first, each with its own condition record.

All of Alaska: Alaska bridge conditions by county · closed and posted bridges nationwide · every download on the data page.

Background: how bridge ratings work · what "poor" and "structurally deficient" actually mean · how often bridges are inspected.