Bridge conditions in Corozal Municipio, Puerto Rico

28 inventoried bridges · 0 closed · 2 posted · 1 rated poor · 2025 National Bridge Inventory

United States Bridge Conditions2025 National Bridge Inventory, FHWACompiled

GoodFairPoor All 28 bridges.

The federal inventory lists 28 bridges in Corozal Municipio: 6 rated good, 21 fair, and 1 poor.

What this page is: the federal bridge inspection inventory for Corozal Municipio: inspector ratings, closures and load postings as reported by the Puerto Rico DOT for the 2025 inventory. It is not a log of incidents, failures or news events.

Good 21.4% · Fair 75.0% · Poor 3.6% of 28 bridges

What changed since the 2024 inventory

Each bridge's 2025 record compared with its 2024 record under the same structure number: condition class, the 0-9 component ratings, and whether it is open, posted or closed. These are changes in inspection ratings, not reports of incidents.

0
dropped into poor
since 2024
0
improved out of poor
since 2024
1
had a rating lowered
deck, superstructure, substructure or culvert
0
newly closed or posted
0 closed, 0 posted

Bridges whose rating or status got worse

BridgeWhat changed20242025Vehicles/day
Pr 159 over Corozal Riversubstructure 7 to 6FairFair8,500

Bridges that improved

BridgeWhat changed20242025Vehicles/day
Pr 568 over Grande Creekload posting removedFairFair1,100
Pr 807 Km 0.1 over Rio Des Los Negrosload posting removedGoodGood100

Closed and load-posted bridges

Bridges coded closed, posted for load, or open only with temporary measures in NBI item 41. A load posting limits the weight a bridge may carry; it is how owners keep a weakened bridge in service safely.

BridgeStatus (item 41)BuiltVehicles/dayLast inspectedCondition
Pr 807 over De Los Negros Riverposted for load195213,800February 2023Fair
Off Pr 818 0.6 Km over Corozal Riverposted for load19668,800August 2024Fair

Status is as reported for the federal inventory, not live. Closures and postings made since then are published by the Puerto Rico department of transportation and the county road department.

Inspections, scour and other flags

Routine inspection intervals (NBI item 91): 4 on 12 months or less, 24 on 24 months. Federal rules set 24 months as the regular maximum, require 12 months or less for bridges with a component rated 3 or lower, and allow up to 48 months for bridges in good shape (23 CFR 650.311).

The most recent inspection on record in Corozal Municipio is dated November 2024; 6 bridges have an inspection dated in 2024.

Scour critical (item 113): 9 bridges. Scour critical means the foundations were found unstable for the assessed or calculated scour, the streambed erosion that floods cause around piers and abutments. Fracture critical (item 92A): 1 bridge. These have steel tension members without a redundant load path and get their own scheduled inspections.

Scour-critical bridges

BridgeStatus (item 41)BuiltVehicles/dayLast inspectedCondition
Off Pr 818 0.6 Km over Corozal Riverposted for load19668,800August 2024Fair
Pr 891 over Corozal Riveropen19186,900June 2024Fair
Pr 818 over Cibuco Riveropen19495,300May 2023Fair
Pr 164 over Depression Small Streamopen19254,200February 2023Fair
Pr 164 over Mavilla Riveropen19254,200February 2023Fair
Calle Julio Torres over _open20183,000February 2023Good
Pr 568 over Creekopen19351,100March 2023Fair
Pr 568 over Creekopen1930200March 2023Fair
Pr 807 Km 0.1 over Rio Des Los Negrosopen2018100November 2024Good

Bridges rated poor

Every bridge in the county with a poor rating, busiest first. Poor means a major component is rated 4 or lower on FHWA's 0-9 scale; it is a repair flag, not a closure notice.

BridgeBuiltVehicles/dayCondition
Off Pr 802 Km .6 over Riachuelo Creek2000600Poor

Busiest bridges in the county

BridgeBuiltVehicles/dayCondition
Pr 142 over Local Road200018,400Good
Pr 142 over Mavilla River200018,400Fair
Pr 142 over Cattle Pass200018,400Good
Pr 807 over De Los Negros River195213,800Fair
Off Pr 818 0.6 Km over Corozal River19668,800Fair
Pr 159 over Corozal River19808,500Fair
Pr 891 over Corozal River19186,900Fair
Pr 159 over Mavilla River19036,200Fair
Pr 159 over Cibuco River19215,400Fair
Pr 818 over Cibuco River19495,300Fair

Frequently asked questions

Are any bridges closed in Corozal Municipio, Puerto Rico?

No bridges of the 28 in Corozal Municipio are coded closed to all traffic in the 2025 National Bridge Inventory, and 2 bridges are posted with load restrictions. The inventory is compiled annually; for closures since then, check the Puerto Rico department of transportation.

Have any bridges failed in Corozal Municipio?

The National Bridge Inventory records inspection ratings, not incidents, so it cannot say whether a bridge failed or made the news. What it does record for Corozal Municipio: no bridges with a component rated 2 (critical) or lower, 1 bridge rated poor overall, and no bridges that dropped into poor condition since the 2024 inventory.

When were bridges in Corozal Municipio last inspected?

Inspection dates in the 2025 inventory for Corozal Municipio run from February 2023 to November 2024. Intervals: 4 on 12 months or less, 24 on 24 months. Most bridges must be inspected at least every 24 months.

Source: FHWA National Bridge Inventory, 2025 (compared with 2024). Counts cover inventoried highway bridges over 20 feet; ratings are reported by the state DOT.

Every bridge in Corozal Municipio → - all 28, busiest first, each with its own condition record.

All of Puerto Rico: Puerto Rico bridge conditions by county · closed and posted bridges nationwide · every download on the data page.

Background: how bridge ratings work · what "poor" and "structurally deficient" actually mean · how often bridges are inspected.