Bridge conditions in Juana Díaz Municipio, Puerto Rico
57 inventoried bridges · 0 closed · 10 posted · 11 rated poor · 2025 National Bridge Inventory
United States Bridge Conditions2025 National Bridge Inventory, FHWACompiled
GoodFairPoor All 57 bridges.
Of the 57 Juana Díaz Municipio bridges in the federal inventory, 11 carry a poor rating. That 19.3% share is roughly 3x the national average.
- 11 of the 57 bridges in Juana Díaz Municipio, Puerto Rico, are rated in poor condition (19.3%) in the 2025 National Bridge Inventory, as of .
- Juana Díaz Municipio has no bridges closed to all traffic and 10 bridges posted with load restrictions in the 2025 National Bridge Inventory (NBI item 41); 3 more bridges are open only on temporary shoring or a temporary structure, or with a posting recommended.
- Since the 2024 inventory, 1 bridge dropped into poor condition and no bridges improved out of it; 6 bridges had at least one major component rating lowered.
- 1 bridge has a deck, superstructure, substructure or culvert rated 2 (critical) or lower, the bottom of FHWA's 0-9 scale.
- Inspection dates on record run from April 2009 to March 2025; 13 bridges over water are coded scour critical.
- 4 bridges (7.0%) are rated good and 42 (73.7%) fair.
- The median Juana Díaz Municipio bridge was built in 1970.
- The busiest poor-rated bridge is Pr 52 Sobd 94.3 Km over Inabon River (built 1970), carrying about 27,300 vehicles a day.
What this page is: the federal bridge inspection inventory for Juana Díaz Municipio: inspector ratings, closures and load postings as reported by the Puerto Rico DOT for the 2025 inventory. It is not a log of incidents, failures or news events.
Good 7.0% · Fair 73.7% · Poor 19.3% of 57 bridges
What changed since the 2024 inventory
Each bridge's 2025 record compared with its 2024 record under the same structure number: condition class, the 0-9 component ratings, and whether it is open, posted or closed. These are changes in inspection ratings, not reports of incidents.
Bridges whose rating or status got worse
| Bridge | What changed | 2024 | 2025 | Vehicles/day |
|---|---|---|---|---|
| Pr 512 6.3 Km over Guayo River | fair to poor; substructure 5 to 3 | Fair | Poor | 4,200 |
| 600M Off Pr 510 over Unnamed Stream | good to fair; deck 8 to 6; superstructure 8 to 7 | Good | Fair | 1,300 |
| Off Pr-149 62.2 Km over Las Brujas Creek | good to fair; substructure 7 to 6 | Good | Fair | 31,600 |
| Pr 506 Km 1.25 over Inabon River | good to fair; deck 7 to 6 | Good | Fair | 11,200 |
| Calle 6 0.14 Km over Stream | deck 7 to 6; superstructure 6 to 5; substructure up 5 to 6 | Fair | Fair | 2,000 |
| Pr 535 4.5 Km over Caimito River | culvert 6 to 5 | Fair | Fair | 1,000 |
Bridges that improved
| Bridge | What changed | 2024 | 2025 | Vehicles/day |
|---|---|---|---|---|
| Pr 52 over Unnamed Creek | load posting removed | Fair | Fair | 56,300 |
| Pr 512 over Guayo River | load posting removed | Fair | Fair | 4,200 |
2 structures in the 2025 inventory do not appear in 2024 under the same number (new or renumbered), and no structures listed in 2024 are no longer listed under their number (replaced, removed or renumbered).
Closed and load-posted bridges
Bridges coded closed, posted for load, or open only with temporary measures in NBI item 41. A load posting limits the weight a bridge may carry; it is how owners keep a weakened bridge in service safely.
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Pr 149 4.5 Km over Guanabana Creek | posted for load | 1924 | 18,500 | June 2024 | Fair |
| Pr 52 Nobd 89.8 Km over Pr 584 9.2 Km | posted for load | 1970 | 17,900 | March 2024 | Fair |
| Pr 1 112.0 Km over Irrigation Channel | posted for load | 1997 | 10,100 | May 2024 | Fair |
| Pr 510 5 Km over Jacaguas River | posted for load | 1973 | 7,100 | June 2024 | Fair |
| Pr 510 over Guanabana Creek | posted for load | 1972 | 5,800 | June 2023 | Fair |
| Off Pr 149 Km 62.5 over Stream | posted for load | 1901 | 4,500 | September 2024 | Poor |
| Pr 512 6.3 Km over Guayo River | posted for load | 1961 | 4,200 | March 2025 | Poor |
| 600M Off Pr 510 over Unnamed Stream | posted for load | 2000 | 1,300 | October 2023 | Fair |
| Off Pr 535 3.4 Km over Canas River | posted for load | 1985 | 1,000 | June 2024 | Poor |
| Off Pr 513 1.8 Km over Creek | posted for load | 1955 | 600 | March 2024 | Fair |
| Pr 52 over Unnamed Creek | open, posting recommended | 1970 | 56,300 | November 2023 | Fair |
| Pr 512 over Guayo River | open, posting recommended | 1961 | 4,200 | September 2023 | Fair |
| Off Pr 512 Km 4.3 over Guayo River | open on a temporary structure | 2006 | 100 | May 2023 | Poor |
Status is as reported for the federal inventory, not live. Closures and postings made since then are published by the Puerto Rico department of transportation and the county road department.
Inspections, scour and other flags
Routine inspection intervals (NBI item 91): 12 on 12 months or less, 45 on 24 months. Federal rules set 24 months as the regular maximum, require 12 months or less for bridges with a component rated 3 or lower, and allow up to 48 months for bridges in good shape (23 CFR 650.311).
The most recent inspection on record in Juana Díaz Municipio is dated March 2025; 2 bridges have an inspection dated in 2025.
Scour critical (item 113): 13 bridges. Scour critical means the foundations were found unstable for the assessed or calculated scour, the streambed erosion that floods cause around piers and abutments. Fracture critical (item 92A): 3 bridges. These have steel tension members without a redundant load path and get their own scheduled inspections.
Scour-critical bridges
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Pr 52 over Unnamed Creek | open, posting recommended | 1970 | 56,300 | November 2023 | Fair |
| Pr 52 Ntbd 94.3 Km over Inabon River | open | 1970 | 27,300 | February 2024 | Fair |
| Pr 52 Sobd 94.3 Km over Inabon River | open | 1970 | 27,300 | July 2024 | Poor |
| Pr 52 Sbd Km 92.6 over Jacaguas River | open | 1970 | 22,700 | February 2024 | Poor |
| Pr 149 4.5 Km over Guanabana Creek | posted for load | 1924 | 18,500 | June 2024 | Fair |
| Pr 52 86.2 Km over CA¥AS River | open | 1970 | 17,900 | March 2024 | Fair |
| Pr 52 Nobd 86.2 Km over CAÑAS River | open | 1970 | 17,900 | March 2024 | Fair |
| Pr 1 108.4 Km over Descalabrado River | open | 1921 | 11,200 | November 2024 | Poor |
| Pr 14 13.9 Km over Jacaguas River | open | 1970 | 6,300 | April 2024 | Fair |
| Off Pr 149 Km 62.5 over Stream | posted for load | 1901 | 4,500 | September 2024 | Poor |
| Pr 512 6.3 Km over Guayo River | posted for load | 1961 | 4,200 | March 2025 | Poor |
| Off Pr 535 3.4 Km over Canas River | posted for load | 1985 | 1,000 | June 2024 | Poor |
| Pr 535 4.5 Km over Caimito River | open | 1948 | 1,000 | April 2024 | Fair |
Bridges with a component rated 2 or lower
2 is critical, 1 imminent failure, 0 failed and out of service on FHWA's scale. Most such bridges are closed or posted.
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Off Pr 512 Km 4.3 over Guayo River | open on a temporary structure | 2006 | 100 | May 2023 | Poor |
Bridges rated poor
Every bridge in the county with a poor rating, busiest first. Poor means a major component is rated 4 or lower on FHWA's 0-9 scale; it is a repair flag, not a closure notice.
| Bridge | Built | Vehicles/day | Condition |
|---|---|---|---|
| Pr 52 Sobd 94.3 Km over Inabon River | 1970 | 27,300 | Poor |
| Pr 52 Nort 92.5 Km over Jacaguas River | 1970 | 22,700 | Poor |
| Pr 52 Sbd Km 92.6 over Jacaguas River | 1970 | 22,700 | Poor |
| Pr 52 Nobd 87.8 Km over Irrigation Channel | 1970 | 17,900 | Poor |
| Pr 14 11.1 Km over GUAYO RIVER & LOCAL | 1980 | 16,200 | Poor |
| Pr 149 66.1 Km over La Joya Creek | 1992 | 14,600 | Poor |
| Pr 1 108.4 Km over Descalabrado River | 1921 | 11,200 | Poor |
| Off Pr 149 Km 62.5 over Stream | 1901 | 4,500 | Poor |
| Pr 512 6.3 Km over Guayo River | 1961 | 4,200 | Poor |
| Off Pr 535 3.4 Km over Canas River | 1985 | 1,000 | Poor |
| Off Pr 512 Km 4.3 over Guayo River | 2006 | 100 | Poor |
Busiest bridges in the county
| Bridge | Built | Vehicles/day | Condition |
|---|---|---|---|
| Pr 52 Sout 94.6 Km over Farm Road | 1971 | 128,150 | Fair |
| Pr 52 over Unnamed Creek | 1970 | 56,300 | Fair |
| Pr 52 Southbound over Pr 535 | 1970 | 35,800 | Fair |
| Off Pr-149 62.2 Km over Las Brujas Creek | 2008 | 31,600 | Fair |
| Pr 52 Nor 94.6 Km over Farm Road | 1971 | 28,150 | Fair |
| Pr 52 Southbound over Descalabrado River | 1970 | 27,900 | Fair |
| Pr 52 Ntbd 94.3 Km over Inabon River | 1970 | 27,300 | Fair |
| Pr 52 Sobd 94.3 Km over Inabon River | 1970 | 27,300 | Poor |
| Pr 149 over Irrigation Channel | 2009 | 24,900 | Good |
| Pr 52 Nobd 93.3 Km over Pr 574 Km 1.0 | 1971 | 22,700 | Fair |
Frequently asked questions
Are any bridges closed in Juana Díaz Municipio, Puerto Rico?
No bridges of the 57 in Juana Díaz Municipio are coded closed to all traffic in the 2025 National Bridge Inventory, and 10 bridges are posted with load restrictions. The inventory is compiled annually; for closures since then, check the Puerto Rico department of transportation.
Have any bridges failed in Juana Díaz Municipio?
The National Bridge Inventory records inspection ratings, not incidents, so it cannot say whether a bridge failed or made the news. What it does record for Juana Díaz Municipio: 1 bridge with a component rated 2 (critical) or lower, 11 bridges rated poor overall, and 1 bridge that dropped into poor condition since the 2024 inventory.
When were bridges in Juana Díaz Municipio last inspected?
Inspection dates in the 2025 inventory for Juana Díaz Municipio run from April 2009 to March 2025. Intervals: 12 on 12 months or less, 45 on 24 months. Most bridges must be inspected at least every 24 months.
Source: FHWA National Bridge Inventory, 2025 (compared with 2024). Counts cover inventoried highway bridges over 20 feet; ratings are reported by the state DOT.
Every bridge in Juana Díaz Municipio → - all 57, busiest first, each with its own condition record.
All of Puerto Rico: Puerto Rico bridge conditions by county · closed and posted bridges nationwide · every download on the data page.
Background: how bridge ratings work · what "poor" and "structurally deficient" actually mean · how often bridges are inspected.