Bridge conditions in Mayagüez Municipio, Puerto Rico
48 inventoried bridges · 0 closed · 13 posted · 7 rated poor · 2025 National Bridge Inventory
United States Bridge Conditions2025 National Bridge Inventory, FHWACompiled
GoodFairPoor All 48 bridges.
About one in 7 bridges in Mayagüez Municipio is rated in poor condition: 7 of 48 on the federal inventory, one of the higher shares in Puerto Rico.
- 7 of the 48 bridges in Mayagüez Municipio, Puerto Rico, are rated in poor condition (14.6%) in the 2025 National Bridge Inventory, as of .
- Mayagüez Municipio has no bridges closed to all traffic and 13 bridges posted with load restrictions in the 2025 National Bridge Inventory (NBI item 41); 6 more bridges are open only on temporary shoring or a temporary structure, or with a posting recommended.
- Since the 2024 inventory, 1 bridge dropped into poor condition and no bridges improved out of it; 5 bridges had at least one major component rating lowered.
- 4 bridges have a deck, superstructure, substructure or culvert rated 2 (critical) or lower, the bottom of FHWA's 0-9 scale.
- Inspection dates on record run from April 2023 to March 2025; 5 bridges over water are coded scour critical.
- 9 bridges (18.8%) are rated good and 32 (66.7%) fair.
- The median Mayagüez Municipio bridge was built in 1974.
- The busiest poor-rated bridge is Pr 2 154.3 Km over YAGUEZ RIVER & URBAN (built 1961), carrying about 45,800 vehicles a day.
What this page is: the federal bridge inspection inventory for Mayagüez Municipio: inspector ratings, closures and load postings as reported by the Puerto Rico DOT for the 2025 inventory. It is not a log of incidents, failures or news events.
Good 18.8% · Fair 66.7% · Poor 14.6% of 48 bridges
What changed since the 2024 inventory
Each bridge's 2025 record compared with its 2024 record under the same structure number: condition class, the 0-9 component ratings, and whether it is open, posted or closed. These are changes in inspection ratings, not reports of incidents.
Bridges whose rating or status got worse
| Bridge | What changed | 2024 | 2025 | Vehicles/day |
|---|---|---|---|---|
| Off Pr 106 12.5 Km over Rio Canas (stream) | fair to poor; culvert 5 to 4 | Fair | Poor | 100 |
| Pr 2 Ramal 4.9 Km over Waterway Channel | good to fair; culvert 7 to 6 | Good | Fair | 57,200 |
| Pr 114 0.2 Km over Sabalos Channel | good to fair; superstructure 7 to 6; substructure 7 to 6 | Good | Fair | 12,300 |
| Pr 2 158.30 Km over Sabalos Channel | substructure 7 to 6 | Fair | Fair | 64,800 |
| Pr 380 1.5 Km over Camino Del Guayo Creek | superstructure 8 to 7 | Fair | Fair | 2,900 |
Bridges that improved
| Bridge | What changed | 2024 | 2025 | Vehicles/day |
|---|---|---|---|---|
| Pr 2 Ramal 2.3 Km over La Salud Creek | load posting removed | Fair | Fair | 51,500 |
| Pr 106 over La Cuchilla Creek | load posting removed | Fair | Fair | 11,800 |
| Off Pr 348 0.9 Km over Grande Creek | load posting removed | Fair | Fair | 8,500 |
| Pr 102 Km 7.5 over Guanajibo River | load posting removed | Poor | Poor | 6,400 |
| Pr-3380 over Quebrada Camino Guayo | load posting removed | Good | Good | 2,900 |
| Local Road over Yaguez River | load posting removed | Poor | Poor | 450 |
3 structures in the 2025 inventory do not appear in 2024 under the same number (new or renumbered), and no structures listed in 2024 are no longer listed under their number (replaced, removed or renumbered).
Closed and load-posted bridges
Bridges coded closed, posted for load, or open only with temporary measures in NBI item 41. A load posting limits the weight a bridge may carry; it is how owners keep a weakened bridge in service safely.
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Pr 2 over De Oro Creek | posted for load | 1961 | 49,500 | April 2023 | Fair |
| Pr 2 over Ditch | posted for load | 1960 | 43,400 | May 2023 | Good |
| Pr 114 over Waterway | posted for load | 1962 | 18,400 | September 2023 | Fair |
| Pr 102 over Yaguez River | posted for load | 1971 | 16,900 | April 2023 | Fair |
| Pr 106 over Yaguez River | posted for load | 1952 | 11,100 | April 2023 | Fair |
| Pr 102 over Majagual Channel | posted for load | 1952 | 10,500 | April 2023 | Fair |
| Pr 106 over Gandel Creek | posted for load | 1884 | 9,400 | November 2024 | Poor |
| Pr 348 over Grande Creek | posted for load | 1970 | 8,500 | April 2023 | Fair |
| Pr 380 1.5 Km over Camino Del Guayo Creek | posted for load | 2005 | 2,900 | April 2024 | Fair |
| Pr 105 over Caricosa Creek | posted for load | 1921 | 2,600 | April 2023 | Fair |
| Off Pr 348 Km 17 over Quebrada Grande | posted for load | 2010 | 600 | June 2023 | Good |
| Pr 352 3.2 Km over Ca%as River | posted for load | 1961 | 500 | November 2023 | Fair |
| Camino Los Lazos over Rio Yaguez | posted for load | 1980 | 100 | September 2023 | Good |
| Pr 2 Ramal 2.3 Km over La Salud Creek | open, posting recommended | 1949 | 51,500 | September 2023 | Fair |
| Pr 2 154.3 Km over YAGUEZ RIVER & URBAN | open on temporary shoring | 1961 | 45,800 | October 2024 | Poor |
| Off Pr 348 0.9 Km over Grande Creek | open, posting recommended | 1984 | 8,500 | June 2024 | Fair |
| Pr 102 Km 7.5 over Guanajibo River | open, posting recommended | 1950 | 6,400 | April 2024 | Poor |
| Pr 354 2.2 Km over Ca%as River | open on a temporary structure | 1957 | 1,100 | August 2024 | Poor |
| Local Road over Yaguez River | open on a temporary structure | 1976 | 450 | March 2025 | Poor |
Status is as reported for the federal inventory, not live. Closures and postings made since then are published by the Puerto Rico department of transportation and the county road department.
Inspections, scour and other flags
Routine inspection intervals (NBI item 91): 6 on 12 months or less, 42 on 24 months. Federal rules set 24 months as the regular maximum, require 12 months or less for bridges with a component rated 3 or lower, and allow up to 48 months for bridges in good shape (23 CFR 650.311).
The most recent inspection on record in Mayagüez Municipio is dated March 2025; 2 bridges have an inspection dated in 2025.
Scour critical (item 113): 5 bridges. Scour critical means the foundations were found unstable for the assessed or calculated scour, the streambed erosion that floods cause around piers and abutments. Fracture critical (item 92A): 3 bridges. These have steel tension members without a redundant load path and get their own scheduled inspections.
Scour-critical bridges
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Pr 2 158.30 Km over Sabalos Channel | open | 1997 | 64,800 | December 2023 | Fair |
| Pr 106 over Gandel Creek | posted for load | 1884 | 9,400 | November 2024 | Poor |
| Off Pr 348 0.9 Km over Grande Creek | open, posting recommended | 1984 | 8,500 | June 2024 | Fair |
| Pr 105 over Caricosa Creek | posted for load | 1921 | 2,600 | April 2023 | Fair |
| Local Road over Yaguez River | open on a temporary structure | 1976 | 450 | March 2025 | Poor |
Bridges with a component rated 2 or lower
2 is critical, 1 imminent failure, 0 failed and out of service on FHWA's scale. Most such bridges are closed or posted.
| Bridge | Status (item 41) | Built | Vehicles/day | Last inspected | Condition |
|---|---|---|---|---|---|
| Pr 2 154.3 Km over YAGUEZ RIVER & URBAN | open on temporary shoring | 1961 | 45,800 | October 2024 | Poor |
| Pr 354 2.2 Km over Ca%as River | open on a temporary structure | 1957 | 1,100 | August 2024 | Poor |
| Local Road over Yaguez River | open on a temporary structure | 1976 | 450 | March 2025 | Poor |
| Local Road over Yaguez River | open | 1976 | 450 | September 2023 | Poor |
Bridges rated poor
Every bridge in the county with a poor rating, busiest first. Poor means a major component is rated 4 or lower on FHWA's 0-9 scale; it is a repair flag, not a closure notice.
| Bridge | Built | Vehicles/day | Condition |
|---|---|---|---|
| Pr 2 154.3 Km over YAGUEZ RIVER & URBAN | 1961 | 45,800 | Poor |
| Pr 106 over Gandel Creek | 1884 | 9,400 | Poor |
| Pr 102 Km 7.5 over Guanajibo River | 1950 | 6,400 | Poor |
| Pr 354 2.2 Km over Ca%as River | 1957 | 1,100 | Poor |
| Local Road over Yaguez River | 1976 | 450 | Poor |
| Local Road over Yaguez River | 1976 | 450 | Poor |
| Off Pr 106 12.5 Km over Rio Canas (stream) | 1980 | 100 | Poor |
Busiest bridges in the county
| Bridge | Built | Vehicles/day | Condition |
|---|---|---|---|
| Pr 2 158.30 Km over Sabalos Channel | 1997 | 64,800 | Fair |
| Pr 2 159.4 Km over Hondo River | 1961 | 60,900 | Good |
| Pr 2 156.4 Km over Majagual Channel | 1958 | 57,700 | Fair |
| Pr 2 Ramal 4.9 Km over Waterway Channel | 1997 | 57,200 | Fair |
| Pr 2 over Sabalo Creek | 1958 | 56,100 | Fair |
| Pr 2 Ramal 2.3 Km over La Salud Creek | 1949 | 51,500 | Fair |
| Pr 2 over De Oro Creek | 1961 | 49,500 | Fair |
| Pr 2 154.3 Km over YAGUEZ RIVER & URBAN | 1961 | 45,800 | Poor |
| Pr 2 over Ditch | 1960 | 43,400 | Good |
| Pr 2R over Yaguez River | 1971 | 23,600 | Fair |
Frequently asked questions
Are any bridges closed in Mayagüez Municipio, Puerto Rico?
No bridges of the 48 in Mayagüez Municipio are coded closed to all traffic in the 2025 National Bridge Inventory, and 13 bridges are posted with load restrictions. The inventory is compiled annually; for closures since then, check the Puerto Rico department of transportation.
Have any bridges failed in Mayagüez Municipio?
The National Bridge Inventory records inspection ratings, not incidents, so it cannot say whether a bridge failed or made the news. What it does record for Mayagüez Municipio: 4 bridges with a component rated 2 (critical) or lower, 7 bridges rated poor overall, and 1 bridge that dropped into poor condition since the 2024 inventory.
When were bridges in Mayagüez Municipio last inspected?
Inspection dates in the 2025 inventory for Mayagüez Municipio run from April 2023 to March 2025. Intervals: 6 on 12 months or less, 42 on 24 months. Most bridges must be inspected at least every 24 months.
Source: FHWA National Bridge Inventory, 2025 (compared with 2024). Counts cover inventoried highway bridges over 20 feet; ratings are reported by the state DOT.
Every bridge in Mayagüez Municipio → - all 48, busiest first, each with its own condition record.
All of Puerto Rico: Puerto Rico bridge conditions by county · closed and posted bridges nationwide · every download on the data page.
Background: how bridge ratings work · what "poor" and "structurally deficient" actually mean · how often bridges are inspected.